(03-12-2020, 07:31 PM)Antti-L Wrote: Well, as you seem to be using VEDA, I think you must have obtained the VEDA DEMO model as well. Please look at the examples in that DEMO model (Scen_UCTest.xls). There is a comparable example (Share of a group of processes within a market ) right in the first sheet (Simple UC).Thanks Antti-L, I looked at the constraint but from what I understand written in this way it would impose the % on each single region while I would like a constraint on the overall production.
To explain myself better, I don't want the % of RES production in region A, region B and region C equal to 40%.
I would like the sum of the electricity production from RES to be 40% (perhaps in region A it is 70% while in B it is 5% and in C it is 20%, decided by optimization)